V
Vickifb
I have a project where I have 5 sub tasks containing subtasks within one
task. I have no partial days, all durations are complet days. The sub tasks
have the following as durations: 61; 94; 87; 72; 43, the main task has
caluclated the duration of 181.88 with a start date of 1/21/08 and finish
date of 9/30/08. I have no predecessors, links or dependencies set.
Any Ideas?
Thanks in Advance Vicki
task. I have no partial days, all durations are complet days. The sub tasks
have the following as durations: 61; 94; 87; 72; 43, the main task has
caluclated the duration of 181.88 with a start date of 1/21/08 and finish
date of 9/30/08. I have no predecessors, links or dependencies set.
Any Ideas?
Thanks in Advance Vicki