V
variant
Okay, just a brief background:
1. Our project is using Physical % Complete to have a subjective way of
marking the tasks complete
2. I know Physical % Complete is not automatically rolled up / calculated
at the summary level
Question: Then how DO you update Physical % Complete at the summary level?
It's non-enterable. Using Physical % Complete to compute for EV fields
doesn't make sense when looking at the project level (as opposed to looking
at it task by task) when you can't change it at any summary task level.
Anyone ever wish there were an option to make Physical % Complete compute at
the summary value - maybe using averages to roll up the value. Wouldn't it
be feasible? (since subtask's Physical % Complete max value = 1 (or 100%))
1. Our project is using Physical % Complete to have a subjective way of
marking the tasks complete
2. I know Physical % Complete is not automatically rolled up / calculated
at the summary level
Question: Then how DO you update Physical % Complete at the summary level?
It's non-enterable. Using Physical % Complete to compute for EV fields
doesn't make sense when looking at the project level (as opposed to looking
at it task by task) when you can't change it at any summary task level.
Anyone ever wish there were an option to make Physical % Complete compute at
the summary value - maybe using averages to roll up the value. Wouldn't it
be feasible? (since subtask's Physical % Complete max value = 1 (or 100%))