N
nickc
I cannot seem to separate planned work and duration from actual. Just now,
I worked with a task that was scheduled for start 4/7 Finish 4/8 work hours
of 16 (2 days 1 person). I tried to adjust on entry table to reflect the
actual start which was 4/7 and actual finish 4/9 with hours still 16 (actual
work) (worked 4/7 & 4/9 not 4/8), and entered remaining work 0. However the
actual work still wants to coincide w/ duration at 3 days (correct) and
actual work at 24 hrs (incorrect). I saw another posting on this where the
person simply had to make sure he entered the remaining work at 0, and
everything seemed to work fine. Must be something simple that I am missing.
I worked with a task that was scheduled for start 4/7 Finish 4/8 work hours
of 16 (2 days 1 person). I tried to adjust on entry table to reflect the
actual start which was 4/7 and actual finish 4/9 with hours still 16 (actual
work) (worked 4/7 & 4/9 not 4/8), and entered remaining work 0. However the
actual work still wants to coincide w/ duration at 3 days (correct) and
actual work at 24 hrs (incorrect). I saw another posting on this where the
person simply had to make sure he entered the remaining work at 0, and
everything seemed to work fine. Must be something simple that I am missing.