progress line not showing delay

T

Tim

I have a schedule with the gantt chart showing 3 bars. My baseline 2 has a
task with 4 days delay, but the progress line is straight vertical all
through the project not peaking left indicating a delay from the original
baseline. How do I get the progress line to compare between baseline 1 and
baseline 2?
 
J

JulieS

Hi Tim,

Progress bars are meant to show variance between actual task progress
and scheduled progress. There are not meant to compare baselines
against each other.

To the best of my knowledge, you'd have to draw those kinds of lines on
the graphic view manually.

I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top