T
Tim
I have a schedule with the gantt chart showing 3 bars. My baseline 2 has a
task with 4 days delay, but the progress line is straight vertical all
through the project not peaking left indicating a delay from the original
baseline. How do I get the progress line to compare between baseline 1 and
baseline 2?