Progress Lines

P

Project Manager

I'm getting a zig zag at the top of my progress line even though it is set to
show the current date. It is starting the progress line at the original
proejct date and then zig zagging the line to the current date. How do i fix
this?
 
R

Rod Gill

My best practices suggest to never ever use progress lines. Better to update
actual start and finish dates and rely on baseline data to show where you
should have been using the Tracking Gantt chart.

Progress lines cause problems, because you have incomplete work in the past
and completed work in the future. How do you determine what your project's
resource needs are for the next few weeks?

By updating as recommended above, all work for next week needs to be done
and all work for last week is complete (provided you have also moved all
incomplete work out to next week after updating your schedule).

Good luck!

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Project Manager said:
I'm getting a zig zag at the top of my progress line even though it is set
to
show the current date. It is starting the progress line at the original
proejct date and then zig zagging the line to the current date. How do i
fix
this?

__________ Information from ESET Smart Security, version of virus
signature database 4978 (20100326) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4978 (20100326) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
T

tom_willpa

high quality Soccer jerseys NBA Jersey tracksuit and jackets, GHD
hairstraightener supplier from www.willpa.com

Are you a Retail businessman who bother by the purchase price? China
Cheapest TOP wholesale website can help you

we are specialize in replica sport goods manufacturing in china, we can
offer you all kinds of soccer jersey, NBA jersey,shoes and so on. they are
the best brand replica goods whih are look the same as the original goods.
excellent quality and steady supply for them. we have been marketed in Europe
and American for 3 year. all the goods we offer are AAA quality. our soccer
jersey are Thailand style. If any goods you buy from my company have problem,
we will refund or resend them again. Most of ourProducts have no minimum
order requirements,soyou can shop retail goods at wholesale prices. if you
can buy more than 300usd. We offer free shipping. The more you buy the more
discount for you.

National soccer jerseys: http://www.willpa.com
Club soccer jerseys: http://www.willpa.com
NBA Jerseys: http://www.willpa.com
T-shirt and shirt: http://www.willpa.com
Tracksuit: http://www.willpa.com
Hoody & Jackets: http://www.willpa.com
UGG boots: http://www.willpa.com
Hair style: http://www.willpa.com
shopping Index: http://www.willpa.com

EMS shipping. 7days arrive, paypal accept

want more information pls contact us or check our website: www.willpa.com
 
P

Project Manager

I don't use the progress lines to indicate what work is done and what work
needs to be completed. I use it as an indication of generally where we are
on a schedule. I have a lot of customer's who don't know how to read a
project schedule, but because of the work and coordination (as managers of a
design process) we need to have one.

so.... this progress line helps my customer to quickly identify on our
project schedule were we are.

still searching for an answer.
 
R

Rod Gill

If the project is updated properly, you are always on today's date: late
work delayed until it restarts, early work pulled forward to when it
actually started, hence progress line redundant.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Project Manager said:
I don't use the progress lines to indicate what work is done and what work
needs to be completed. I use it as an indication of generally where we
are
on a schedule. I have a lot of customer's who don't know how to read a
project schedule, but because of the work and coordination (as managers of
a
design process) we need to have one.

so.... this progress line helps my customer to quickly identify on our
project schedule were we are.

still searching for an answer.



__________ Information from ESET Smart Security, version of virus
signature database 4980 (20100328) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4980 (20100328) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
B

bernward

Your are right, if you have choose progessline in relation to actual
plan.
When you change the option "display progress lines" from "actual plan"
to "Baseline plan" you get the correct progressline. But it is
littlebit confusing to see the progress line in a ganttchart with
baselineinformation.
 