Project has always worked just fine. I have not changed anything, but now,
all of a sudden, many things are not working (this is affecting others in my
organization as well):
-Pressing "Enter" will not automatically go to the next line
-Entering a predecessor with finish-to-start will NOT update the start time
for the task
-Entering subtasks will not update the finish date of the parent task (even
if the subtasks are scheduled to finish later than the parent task)
I have not changed anything and I don't know what is going on. Everyone
else I have talked to in the organization is having the same issue. Any help
is appreciated.
all of a sudden, many things are not working (this is affecting others in my
organization as well):
-Pressing "Enter" will not automatically go to the next line
-Entering a predecessor with finish-to-start will NOT update the start time
for the task
-Entering subtasks will not update the finish date of the parent task (even
if the subtasks are scheduled to finish later than the parent task)
I have not changed anything and I don't know what is going on. Everyone
else I have talked to in the organization is having the same issue. Any help
is appreciated.