We created a Master Project in PS2007 and inserted sub-projects in it as
read-only.
But when we publish the Master Project it also publishes assignments updates
of the sub-projects although these projects are read-only.
We would like to avoid it.
I was thinking of breaking the Link and Publishing it and re-establish the
link after publishing the master.
Alright I broke the link and published the master now the resources gets an
email that they are assigned to the Master.
and then i cannot re-establish the link to the sub-project.
Any thoughts ?
read-only.
But when we publish the Master Project it also publishes assignments updates
of the sub-projects although these projects are read-only.
We would like to avoid it.
I was thinking of breaking the Link and Publishing it and re-establish the
link after publishing the master.
Alright I broke the link and published the master now the resources gets an
email that they are assigned to the Master.
and then i cannot re-establish the link to the sub-project.
Any thoughts ?