Hi All,
The scenario I have is this: I have a task on Monday that is an 8 hour
meeting for which I am applying 5 resources. I've set the task to Fixed
Duration and turned off the effort driven scheduling to be able to
capture each resource's hourly rate for 8 hours each. When I apply the
5th resource (myself), I receive the message: The resource is assigned
outside the original dates for ... The duration of this FD task with
change... The task then changes to 2 days overriding the FD I need.
The only difference between me and the others is that I have applied
myself to a "Standard - Weekends" schedule that includes Sat/Sun as
working days (I have no non-work days or exceptions built-in). This is
my default schedule. If however I change my default schedule back to
Standard I do not receive the message. Further, If I set my default to
Standard then assign me to the task, then go back to the Resource Sheet
to change to Standard - Weekends, I get the same message in the RS table
about this task.
Any help in explaining this or providing ideas as to where I might look
for the cause would be greatly appreciated!
Dan
The scenario I have is this: I have a task on Monday that is an 8 hour
meeting for which I am applying 5 resources. I've set the task to Fixed
Duration and turned off the effort driven scheduling to be able to
capture each resource's hourly rate for 8 hours each. When I apply the
5th resource (myself), I receive the message: The resource is assigned
outside the original dates for ... The duration of this FD task with
change... The task then changes to 2 days overriding the FD I need.
The only difference between me and the others is that I have applied
myself to a "Standard - Weekends" schedule that includes Sat/Sun as
working days (I have no non-work days or exceptions built-in). This is
my default schedule. If however I change my default schedule back to
Standard I do not receive the message. Further, If I set my default to
Standard then assign me to the task, then go back to the Resource Sheet
to change to Standard - Weekends, I get the same message in the RS table
about this task.
Any help in explaining this or providing ideas as to where I might look
for the cause would be greatly appreciated!
Dan