B
Bruce McF
MSPP 2007 SP1: Recurring tasks don't rollup on to the group by summary bar.
We set the background color of the Group on Summary bar to yellow and then
rollup the projections of the tasks in the group in gray. (Always Rollup
Gantt Bars is checked.) The resulting summary bar shows yellow for
weekends and any gaps in the time not "covered" by a task.
Normal tasks rollup just fine, but the recurring tasks seem to be invisible
to the rollup. Is there information on what special attributes are set for
recurring tasks? Perhaps, with this info, we could figure out why the
recurring tasks don't roll up to display on the grouped summary bar.
Thanks,
Bruce
(When grouped and collapsed, the rolled up summary bar shows where there are
gaps in assigned work .. for whatever reason.)
We set the background color of the Group on Summary bar to yellow and then
rollup the projections of the tasks in the group in gray. (Always Rollup
Gantt Bars is checked.) The resulting summary bar shows yellow for
weekends and any gaps in the time not "covered" by a task.
Normal tasks rollup just fine, but the recurring tasks seem to be invisible
to the rollup. Is there information on what special attributes are set for
recurring tasks? Perhaps, with this info, we could figure out why the
recurring tasks don't roll up to display on the grouped summary bar.
Thanks,
Bruce
(When grouped and collapsed, the rolled up summary bar shows where there are
gaps in assigned work .. for whatever reason.)