jimmyg
I have a pm who manually removed 6000 hours of actual
time from a plan located on the project server. The next
time the plan was used, after several periodic saves, an
odbc error occurred and the plan crashed. After this the
circular reference error message started appearing.
Could this have been caused by removing so much actual
time that was associated with a large number of resources?
thanks
time from a plan located on the project server. The next
time the plan was used, after several periodic saves, an
odbc error occurred and the plan crashed. After this the
circular reference error message started appearing.
Could this have been caused by removing so much actual
time that was associated with a large number of resources?
thanks