W
whstewart1
I am relatively new to project and perhaps starting out with
complicated scenario. I am getting ready to start fixing up a 50 uni
apartment complex with the residents still living there. Due to this
my scheduling has to go down to the hour of each of 2 or 3 days that w
move the residents out. I want to know the best way of managing thi
relatively simple task and multiplying it by 50 (once for each unit)
started out by having each task as a sub task of the day of work and th
2 days of work as subtasks for the apartment unit that I am working o
at that specific time. The problem is- I want to be able to change th
schedule for the first Unit and for it to apply to all 50 units.
Basically I want to have the same set of tasks repeated 50 times and b
able to adjust or add to only one of them and have it change all of th
rest. Is there any clean way of doing this. I was thinking of makin
each unit a separate project and having a master project to run th
whole thing but that does not solve the problem of if I need to chang
the schedule because one item is taking longer than expected. I do no
want to have to go in and to that on all 50 files or in all 50 subtask
if it is all in 1 project. Any ideas would be greatly appreciated
complicated scenario. I am getting ready to start fixing up a 50 uni
apartment complex with the residents still living there. Due to this
my scheduling has to go down to the hour of each of 2 or 3 days that w
move the residents out. I want to know the best way of managing thi
relatively simple task and multiplying it by 50 (once for each unit)
started out by having each task as a sub task of the day of work and th
2 days of work as subtasks for the apartment unit that I am working o
at that specific time. The problem is- I want to be able to change th
schedule for the first Unit and for it to apply to all 50 units.
Basically I want to have the same set of tasks repeated 50 times and b
able to adjust or add to only one of them and have it change all of th
rest. Is there any clean way of doing this. I was thinking of makin
each unit a separate project and having a master project to run th
whole thing but that does not solve the problem of if I need to chang
the schedule because one item is taking longer than expected. I do no
want to have to go in and to that on all 50 files or in all 50 subtask
if it is all in 1 project. Any ideas would be greatly appreciated