G
Guest
Hi,
I would like to generate a report (or view that I can export to Excel)
that lists
work for resources that work in WBS id x by year.
So I have
1 Summary task X
1.1 Task 1: A 20hrs, B 20hrs
1.2 Task 2: A 0hrs, B 20hrs
1.3 Task 3: A 0hrs, B 20hrs, C 20hrs
2 Summary task Y
2.1 Task 4: A 20hrs, B 20hrs
2.2 Task 5: A 20hrs, B 20hrs
and the the report for WBS X should look like
A 20hrs
B 60hrs
C 20hrs
The one for WBS Y should look like
A 40hrs
B 40hrs
Ideally, the report has more than one column - one for each year.
What sounds simple appears to be more complex in project. At least I
could
not find any article that describes such a report and fiddling around
with
the task usage view has not been successfull, yet. Any hints
appreciated.
Thank you,
Stefan.
I would like to generate a report (or view that I can export to Excel)
that lists
work for resources that work in WBS id x by year.
So I have
1 Summary task X
1.1 Task 1: A 20hrs, B 20hrs
1.2 Task 2: A 0hrs, B 20hrs
1.3 Task 3: A 0hrs, B 20hrs, C 20hrs
2 Summary task Y
2.1 Task 4: A 20hrs, B 20hrs
2.2 Task 5: A 20hrs, B 20hrs
and the the report for WBS X should look like
A 20hrs
B 60hrs
C 20hrs
The one for WBS Y should look like
A 40hrs
B 40hrs
Ideally, the report has more than one column - one for each year.
What sounds simple appears to be more complex in project. At least I
could
not find any article that describes such a report and fiddling around
with
the task usage view has not been successfull, yet. Any hints
appreciated.
Thank you,
Stefan.