C
Carlos H Moller
hi folks!
i've this scenario using Project Professional 2003, with SP2 applied...
1- my Default Start Time is 8:30 and Default End Time is 18:00, so 7,5 hours
per day (1 hour for lunch break).
2- i have defined this on Tools->Options->Calendar Tab. Also defined Hours
Per Day 7,5 and Hours per Week 37,5.
3- i have created a Calendar named Test (copy of the Standard calendar) for
the project and resources and both are using the settings above.
4- when a Resource (which has the Test Calendar assigned) has a 1 day task,
the Resource Usage View shows 7,5h. that's fine!
5- when the same Resource has a 2 day task or a 3 day task, Project 2003
splits the hours this way:
a- for a 2 day task: 8h and 7h
b- for a 3 day task: 8h, 8h and 6,5h.
i know the sum is ok, but why does it show that way?
thanks for any help!
c h moller
i've this scenario using Project Professional 2003, with SP2 applied...
1- my Default Start Time is 8:30 and Default End Time is 18:00, so 7,5 hours
per day (1 hour for lunch break).
2- i have defined this on Tools->Options->Calendar Tab. Also defined Hours
Per Day 7,5 and Hours per Week 37,5.
3- i have created a Calendar named Test (copy of the Standard calendar) for
the project and resources and both are using the settings above.
4- when a Resource (which has the Test Calendar assigned) has a 1 day task,
the Resource Usage View shows 7,5h. that's fine!
5- when the same Resource has a 2 day task or a 3 day task, Project 2003
splits the hours this way:
a- for a 2 day task: 8h and 7h
b- for a 3 day task: 8h, 8h and 6,5h.
i know the sum is ok, but why does it show that way?
thanks for any help!
c h moller