Marc D
The scenario is the following:
I have one particular task that will have to be worked overnight rather than
during regular hours. I have indicated that that task use the night
schedule. The same resources working on other tasks will be working on this
one except at a different time. However, the resources will only work either
during the night OR during the day. Project schedules both night and day
work on the same day for the same resources so they end up work double
shifts. How can I restrict the amount of work done per resource per day? I
want to schedule the overnight task on separate days as the regular time
tasks.
I have one particular task that will have to be worked overnight rather than
during regular hours. I have indicated that that task use the night
schedule. The same resources working on other tasks will be working on this
one except at a different time. However, the resources will only work either
during the night OR during the day. Project schedules both night and day
work on the same day for the same resources so they end up work double
shifts. How can I restrict the amount of work done per resource per day? I
want to schedule the overnight task on separate days as the regular time
tasks.