D
david44
Hello
I'm another newbie to the forum, having completed a UK based Microsoft
Introduction and Intermediate Training Course for Project 2007 a couple of
months ago.
I'm currently running, a Master File with 8 Projects - all running
sucessfully, but wish to revise the Resource Pool. I've put together a
Revised Resource Pool10 and would like to reassign to my existing Projects.
The Resource sharing Links show the connection to a previous Resource Pool2,
even after I try to disconnect the Link.
In desperation I've completely deleted my previous Resource Pool2 - trying
to connect to my new Resource Pool10.
Unfortunitely the Share Resources options still list the deleted files, with
no Reference or Option to link to my new Resource Pool10.
Ultimately, I wish to print out reports from my Master File, giving the
Total Resource Hrs covering all Projects.
In a quandery - What do I do from here ????
No doubt this a no brainer to those well versed with Project.
Look forward to hearing from you soon
Regards
david44
I'm another newbie to the forum, having completed a UK based Microsoft
Introduction and Intermediate Training Course for Project 2007 a couple of
months ago.
I'm currently running, a Master File with 8 Projects - all running
sucessfully, but wish to revise the Resource Pool. I've put together a
Revised Resource Pool10 and would like to reassign to my existing Projects.
The Resource sharing Links show the connection to a previous Resource Pool2,
even after I try to disconnect the Link.
In desperation I've completely deleted my previous Resource Pool2 - trying
to connect to my new Resource Pool10.
Unfortunitely the Share Resources options still list the deleted files, with
no Reference or Option to link to my new Resource Pool10.
Ultimately, I wish to print out reports from my Master File, giving the
Total Resource Hrs covering all Projects.
In a quandery - What do I do from here ????
No doubt this a no brainer to those well versed with Project.
Look forward to hearing from you soon
Regards
david44