K
Kjell Andersson
Hi !
I have a problem in MS-project, I have a masterplan in MS-project that
contains several other MS-project plans and they have a whole bunch of
activities and some milestones here comes the problem, when i set the
milestone tasks to be rolled up to the main subproject bar for each
subproject i get a milestone symbol at the main sub project bar but the
name does not show up, what should i do to get the name rolled up to ?
Best regards Kjell A
I have a problem in MS-project, I have a masterplan in MS-project that
contains several other MS-project plans and they have a whole bunch of
activities and some milestones here comes the problem, when i set the
milestone tasks to be rolled up to the main subproject bar for each
subproject i get a milestone symbol at the main sub project bar but the
name does not show up, what should i do to get the name rolled up to ?
Best regards Kjell A