I have loaded Project 2007 with all the tasks for a project that has been in
progress since last October. There are about 500 tasks. About 100 have been
completed, about 50 are in progress, and the rest have yet to be started. I
have assigned resources to all the tasks, and actual start and finish dates
in the past for all completed tasks.
I want the program to schedule and level only the remaining work starting
from today. So far all I have been able to accomplish is scheduling all the
work, including the completed tasks, from the project start date. How do I
schedule only the remaining work correctly from now, but keep all the
completed tasks in the plan?
progress since last October. There are about 500 tasks. About 100 have been
completed, about 50 are in progress, and the rest have yet to be started. I
have assigned resources to all the tasks, and actual start and finish dates
in the past for all completed tasks.
I want the program to schedule and level only the remaining work starting
from today. So far all I have been able to accomplish is scheduling all the
work, including the completed tasks, from the project start date. How do I
schedule only the remaining work correctly from now, but keep all the
completed tasks in the plan?