M
MarkC
Take a look at the following tasks using 2003 sp3, you will notice 2 tasks
start at 17:00. This is a standard project using the standard calendar with
all activties having FS with no lag and all have "start as soon as possible"
Durn Start Finish
25 days 07/09/09 08:00 09/10/09 17:00
15 days 09/10/09 17:00 30/10/09 17:00
10 days 02/11/09 08:00 13/11/09 17:00
10 days 16/11/09 08:00 27/11/09 17:00
5 days 30/11/09 08:00 04/12/09 17:00
5 days 04/12/09 17:00 11/12/09 17:00
30 days 14/12/09 08:00 22/01/10 17:00
Why do the 2nd and 6th activities start at 17:00? I have even deleted the
logic prior to the activity and re-assigned it. I have changed the durations
and still no change to 17:00. Why?
start at 17:00. This is a standard project using the standard calendar with
all activties having FS with no lag and all have "start as soon as possible"
Durn Start Finish
25 days 07/09/09 08:00 09/10/09 17:00
15 days 09/10/09 17:00 30/10/09 17:00
10 days 02/11/09 08:00 13/11/09 17:00
10 days 16/11/09 08:00 27/11/09 17:00
5 days 30/11/09 08:00 04/12/09 17:00
5 days 04/12/09 17:00 11/12/09 17:00
30 days 14/12/09 08:00 22/01/10 17:00
Why do the 2nd and 6th activities start at 17:00? I have even deleted the
logic prior to the activity and re-assigned it. I have changed the durations
and still no change to 17:00. Why?