Shared resource pool not working?! help please!

E

Elle

I’ve created a shared resource pool for an integrated programme level plan,
but when I enter the resource on the gantt chart view it’s just adding
another resource on the resource sheet, it isn’t taking what I’ve written as
the resource in the resource pool, even though they are exactly the same.

Why is it doing this? Because I don’t see the point in having a shared
resource pool if this is the case??

Thanks
 
M

Mike Glen

Hi Elle,

Welcome to this Microsoft Project newsgroup :)

You need to share the resources with the pool via Tools/Resource
sharing/Share resources... and select the pool. When you've done this for
every project, create a new master file and import each project. The
procedures are shown in my free series on Microsoft Project in the TechTrax
ezine, particularly #17 & 18 on multiple projects, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 