tommcbrny
Hello,
I imagine this question has been asked many times, but several searches
through the group yielded no answer.
I have resources who have multiple concurrent assignments. Is there a way
to have Project split the resource's time among the concurrent assignments
automatically, or do I need to set this manually?
Currently, I add tasks and assign a resource, and then project sets the
resource to work 8 hours per day on each task resulting in an overallocation.
Leveling pushes the tasks out serially, so task 1 is worked to completion,
then task 2, etc.
I'd like Project to split the resource's time among the tasks automatically
and not overallocate the resource if possible.
Thanks,
Tom
I imagine this question has been asked many times, but several searches
through the group yielded no answer.
I have resources who have multiple concurrent assignments. Is there a way
to have Project split the resource's time among the concurrent assignments
automatically, or do I need to set this manually?
Currently, I add tasks and assign a resource, and then project sets the
resource to work 8 hours per day on each task resulting in an overallocation.
Leveling pushes the tasks out serially, so task 1 is worked to completion,
then task 2, etc.
I'd like Project to split the resource's time among the tasks automatically
and not overallocate the resource if possible.
Thanks,
Tom