P
PatrickatKAZ
The task duration of a summary task shows as zero if the sub-tasks are
assigned to resources that have non-default working days. For example,
resource A calendar has Saturday & Sunday as non standard work days but the
Standard (Project Calendar) has these days as non-working days. The detail
tasks have a 2 day duration (ie. Sat & Sun) but the summary task shows as
zero duration. Is there any option/setting to address this ? (I use MS
Project 2003).
assigned to resources that have non-default working days. For example,
resource A calendar has Saturday & Sunday as non standard work days but the
Standard (Project Calendar) has these days as non-working days. The detail
tasks have a 2 day duration (ie. Sat & Sun) but the summary task shows as
zero duration. Is there any option/setting to address this ? (I use MS
Project 2003).