T
Ted M H
I'm working with a simple project with about 15 summary tasks. All summary
tasks have at least 1 detail task and some have up to three detail tasks.
Most of the Summary tasks accurately show the duration, but 3 - 4 of them
simply show 0 as the duration (Everything I'm doing is in hours, by the way),
even though the detail tasks are not zero duration.
Oddly, the start and finish dates and times are calculated just fine for the
summary tasks--it's just the duration that's the problem.
The only clue I have is that the zero duration summary tasks were somehow
designated as milestones in task information. Clearing the mark as milestone
check box however doesn't change anything.
Any suggestions?
tasks have at least 1 detail task and some have up to three detail tasks.
Most of the Summary tasks accurately show the duration, but 3 - 4 of them
simply show 0 as the duration (Everything I'm doing is in hours, by the way),
even though the detail tasks are not zero duration.
Oddly, the start and finish dates and times are calculated just fine for the
summary tasks--it's just the duration that's the problem.
The only clue I have is that the zero duration summary tasks were somehow
designated as milestones in task information. Clearing the mark as milestone
check box however doesn't change anything.
Any suggestions?