rathan
I want to create a plan which contains a column which displays a
Graphical-indicator.
I want to display the indicator with respect to two things.duration and
task completion.
i am aware that we can use %complete(duration), and physical
%complete(task completion).
we may caluculate the differece between these two,and with respect to
the value we can display the indicator.for example the difference is 0%
or less then we can display Green.if is moderate then we can display
Amber..if the difference being high the we can warn with a Red
indicaor.
My problem is when we use physical %complete, we enter the values
manually in the subtasks.But the summary task value is not getting
updated accordingly.Because of this i am unable to use it..Anyone can
suggest any alternate method so that i can display an stoplight
indicator with respect to duration completion and task completion.
Graphical-indicator.
I want to display the indicator with respect to two things.duration and
task completion.
i am aware that we can use %complete(duration), and physical
%complete(task completion).
we may caluculate the differece between these two,and with respect to
the value we can display the indicator.for example the difference is 0%
or less then we can display Green.if is moderate then we can display
Amber..if the difference being high the we can warn with a Red
indicaor.
My problem is when we use physical %complete, we enter the values
manually in the subtasks.But the summary task value is not getting
updated accordingly.Because of this i am unable to use it..Anyone can
suggest any alternate method so that i can display an stoplight
indicator with respect to duration completion and task completion.