Summary Tasks and Master Project Plans

J

John Cello

Justine:

When you did the Insert...Project, did you select the
checkbox labeled "Link to project" ?

John Cello
John Cello Consulting
Communications For Business
www.johncelloconsulting.com
-----Original Message-----
Hello,

I have created a Master project plan to encompass all of
the projects that we are working on in our department.
Each individual project has it's own plan and is
incorporated into the Master. The "summary task"
contains the project name for each inserted project as
well as high level information for each project. It
appears that the summary task does not link from the
individual project plan to the master project plan. What
I mean is that the summary task in the "individual"
project plan does not automatically update the summary
task in the "master" project plan (and vice versa). Why
is that? Is there a setting somewhere that can make this
happen?
 