ShawnMc
I have a software development plan in front of me, and our deployment
activity must occur on a Saturday. I've already learned how to force Project
to start the task on Saturday using a "dummy resource" named "Saturday" and
adjusting that resource's working time to only be Saturday. Here's my
problem, however:
The deployment activities themselves (about 30 tasks) are performed by a
series of resources who don't normally work on Saturday. How do I tell
Project to let them work ONLY the Saturday of the deployment? If I open them
up to have Saturday as a working day, they work EVERY Saturday. If I only
open them up on the deployment Saturday, and do so manually, I eliminate the
scheduling power of Project.
Ideas? Thanks in advance!!
activity must occur on a Saturday. I've already learned how to force Project
to start the task on Saturday using a "dummy resource" named "Saturday" and
adjusting that resource's working time to only be Saturday. Here's my
problem, however:
The deployment activities themselves (about 30 tasks) are performed by a
series of resources who don't normally work on Saturday. How do I tell
Project to let them work ONLY the Saturday of the deployment? If I open them
up to have Saturday as a working day, they work EVERY Saturday. If I only
open them up on the deployment Saturday, and do so manually, I eliminate the
scheduling power of Project.
Ideas? Thanks in advance!!