T
Tito
I'm having a problem with elapsed days and negative slack values. The total
slack values calculate correctly for Edays whenever you have positive slack.
Once I change the constraint on the completion date to create a negative
total slack value, the Eday calculation is wrong.
Example -
1. create a simple string of tasks with each task 5 days in duration.
2. Add a constraint to the final task in this string which causes your total
slack value to be negative.
3. Change any one of the durations from 5d to 5ed and you'll see the
negative slack value get larger instead of smaller i.e., -25.38d instead of
-20d like all of the other tasks in that chain.
I actually expected the total slack to decrease below -20d....
slack values calculate correctly for Edays whenever you have positive slack.
Once I change the constraint on the completion date to create a negative
total slack value, the Eday calculation is wrong.
Example -
1. create a simple string of tasks with each task 5 days in duration.
2. Add a constraint to the final task in this string which causes your total
slack value to be negative.
3. Change any one of the durations from 5d to 5ed and you'll see the
negative slack value get larger instead of smaller i.e., -25.38d instead of
-20d like all of the other tasks in that chain.
I actually expected the total slack to decrease below -20d....