J
Jeff
Hello- New user here. I am in the process of setting up a "global" calendar
for our company by jobs. I set up each job as a task, and I set up the
facets of the job as sub-tasks. My challenge is that not all of my dates for
given sub-tasks are concurrent, however it ends up showing a total "calendar"
period for total days of the task. For example- On Job A- we might start the
demolition of a project on 7/1/09 lasting 4 days (a sub-task of Job A). We
will maybe go back on 8/1/09 for another 4 days for an additional sub-task.
The duration will show 30 days, when actual task duration is a total of 8
days. How do I get the Task Duration to show the actual 8 days worked?
Thanks,
for our company by jobs. I set up each job as a task, and I set up the
facets of the job as sub-tasks. My challenge is that not all of my dates for
given sub-tasks are concurrent, however it ends up showing a total "calendar"
period for total days of the task. For example- On Job A- we might start the
demolition of a project on 7/1/09 lasting 4 days (a sub-task of Job A). We
will maybe go back on 8/1/09 for another 4 days for an additional sub-task.
The duration will show 30 days, when actual task duration is a total of 8
days. How do I get the Task Duration to show the actual 8 days worked?
Thanks,