T
TKGerdie
Is it possible in MS Project 2007 to report actual quantities completed vs. %
complete or hours complete?
Example - Our crew has 1500 linear feet on their task of directional boring.
They have completed 750 linear feet. This is how we want to enter our
updates - is this possible?
complete or hours complete?