Tracking actual resource time in Project 2003

J

JennyK

We have recently implemented Project 2003 EPM.

Our main issue with resource actuals is that we plan time in Project 2003
but use a separate and different timesheeting system.

The data we get out of the timesheeting system is not at the sufficient
level to go back to the plan and put actuals against each task (it is a
rolled up amount per project per week).

Has anyone got a method for resolving this? Many thanks
 