M
Mike M
Is there a way to record actual time in a daily activity log within Project
2003/2007?
Basically, once a task has been started, I would like to log on a daily
basis until the project is complete, the number of hours spent per day. For
example, for a 1 day task starting on Monday. I spend my time in the
following way.
Monday: 1 hour
Tuesday: 5 hours
Wednesday: 0 hours
Thursday: 4 hours. !!! Task Complete !!!
Total time 10 hours. Actual Start: Monday Actual Finish Thursday. In the
end, I want to visualize a 10 hour effort stretched out over a 4 day period
then analyze what other tasks interrupted the scheduled work.
Is it possible to use create an activity log per task in Project 2k3/7? If
so, how?
2003/2007?
Basically, once a task has been started, I would like to log on a daily
basis until the project is complete, the number of hours spent per day. For
example, for a 1 day task starting on Monday. I spend my time in the
following way.
Monday: 1 hour
Tuesday: 5 hours
Wednesday: 0 hours
Thursday: 4 hours. !!! Task Complete !!!
Total time 10 hours. Actual Start: Monday Actual Finish Thursday. In the
end, I want to visualize a 10 hour effort stretched out over a 4 day period
then analyze what other tasks interrupted the scheduled work.
Is it possible to use create an activity log per task in Project 2k3/7? If
so, how?