I
Ivanchem
Hi
I have a trouble in MS Project Pro 2007 SP1.
1. I had exported data from Project 2007 SP1 with use existing map
"Task Export Table map" to Excel.
2. I had Opened exported data in Excel 2007 Sp1 and I've corrected
value "Percent_Complete" in some task
3. I am importing data back to project with use existing map "Task
Export Table map" and "Merge the data into the active project"
Trouble: All Links between task have been cleared.
This issue stand up after SP1.
I have a trouble in MS Project Pro 2007 SP1.
1. I had exported data from Project 2007 SP1 with use existing map
"Task Export Table map" to Excel.
2. I had Opened exported data in Excel 2007 Sp1 and I've corrected
value "Percent_Complete" in some task
3. I am importing data back to project with use existing map "Task
Export Table map" and "Merge the data into the active project"
Trouble: All Links between task have been cleared.
This issue stand up after SP1.