R
Ryan
Good Morning
I have a situation where the unit of work for all users logging into Project
Server 2007 via PWA is not the same on the My Tasks page.
When I test it via my admin account and a test user account, it displays as
hours which is the correct setting. Other users however see the unit as days
which means that the system either converts the hours into a fraction of a
day (confusing for the user) or if they don't enter the number of hours with
an "h" with it in the timephase grid, it multiplies it by our work day so
that for instance 8hrs becomes 64hrs (8 x 8hrs/day).
Has anyone seen this?
Ryan
I have a situation where the unit of work for all users logging into Project
Server 2007 via PWA is not the same on the My Tasks page.
When I test it via my admin account and a test user account, it displays as
hours which is the correct setting. Other users however see the unit as days
which means that the system either converts the hours into a fraction of a
day (confusing for the user) or if they don't enter the number of hours with
an "h" with it in the timephase grid, it multiplies it by our work day so
that for instance 8hrs becomes 64hrs (8 x 8hrs/day).
Has anyone seen this?
Ryan