C
Chama
Our MS Project files are maintained in the ClearCase configuration management
tool. When I build the Resource pool from our schedules the links shown
include
"\joe.graham_view\" as part of the path.
When our project managers update their schedules and refresh resource pool
another path is created with their view name as part of the path for example,
"\molly.curl_view\"
MS Project treats this schedule as if it were an additional schedule to the
resource pool and we end up with two identical schedules in the pool with
different path names.
Has anyone encountered this problem and know a solution? Taking our
schedules is not an option available to me.
tool. When I build the Resource pool from our schedules the links shown
include
"\joe.graham_view\" as part of the path.
When our project managers update their schedules and refresh resource pool
another path is created with their view name as part of the path for example,
"\molly.curl_view\"
MS Project treats this schedule as if it were an additional schedule to the
resource pool and we end up with two identical schedules in the pool with
different path names.
Has anyone encountered this problem and know a solution? Taking our
schedules is not an option available to me.