F
Fei
The baseline work estimated for a task is 12 hours. Later when I became more
clear of the requirement I entered 10 hours into Work field of the task as a
more accurate value.
When I completed this task I realized that I only spent 5 hours on the task,
I entered this value into Actual Work.
The %work completed should be 100%. When I went to change the % Work
Completed to 100% the Actual Work automatically changed to 10 hours. Then I
when I changed the Actual Work back to 5 hours, the % Work Completed
automatically changed to 50%........
According to the definition, % Work Completed= Actual Work / Work.
Is it possible to keep this set of value at all:
Work = 10 hours
Actual Work = 5 hours
% Work Completed = 100%
thanks in advanced!
clear of the requirement I entered 10 hours into Work field of the task as a
more accurate value.
When I completed this task I realized that I only spent 5 hours on the task,
I entered this value into Actual Work.
The %work completed should be 100%. When I went to change the % Work
Completed to 100% the Actual Work automatically changed to 10 hours. Then I
when I changed the Actual Work back to 5 hours, the % Work Completed
automatically changed to 50%........
According to the definition, % Work Completed= Actual Work / Work.
Is it possible to keep this set of value at all:
Work = 10 hours
Actual Work = 5 hours
% Work Completed = 100%
thanks in advanced!