Hi,

I have just started using Project Pro 2007.

I am trying to import a fairly simple list of tasks from an excel
spreadsheet.

All my tasks at 0% import (myPercentageColumn -> % Complete) and show
%100. If i import a percentage at 1% or higher it imports fine.

I have switched off all calculations on the Tools -> Options ->
Calculation tab.

I just wondered if this was a known issue before I start investigating
further.

Regards
Dan
 
M

Mike Glen

Hi Dan,

Are you using Project Server? If so, try posting on the server newsgroup.
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top