Are calendars related to each others?

P

Pinocchio

When you create a new calendar based on an existing one, do both calendars
stay related (syncronized) after the copy?
If so, where can I find the updating/cascading rules?

Your MVB (Most Valuable Beginner)
Running Project 2002
 
J

Jan De Messemaeker

Hi,
New base calendars do not update each other
Resource calendars based on a base calendar get updatesd when the bese
calendar is.
HTH
 
P

Pinocchio

Thanks Jan,

For my understanding, is it correct to say that a resource calendar is just
a layer above a base calendar.
If nothing is defined for a given date (use default) in the resource
calendar, then the base calendar working time is defaulted.
If working time is defined for a given date (as nonworking time or
nondefault working time), then the working time defined in the base calendar
is ignored.

Which would mean that changes in the underlying base calendar impact a
resource calendar only for the dates defined as "use default" working time.

Furthermore, all base calendars are defined above a "granite" calendar
defining unmodifiable (8:00-12:00 13:00-17:00) working times.
Calendars in MS Projects are defined on three levels: "Granite" Calendar /
Base Calendars / Resource Calendars, where you see the underlying calendar
definition only if you define "use default" working time.

I hope I understood the mechanism correctly.
Your MVB (Most Valuable Beginner)
Running Project 2002
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top