A
ABH
General question. Does project allow task priorities in
the defined range of 0 to 1000? I have tried to isolate
groups of tasks in 550/530/520 bands and this performs the
resource levelling (set to Priority, Standard) correctly.
When I close the project however, these values are lost
and all default to 600.
Yours confused, Alan Barrington-Hughes
the defined range of 0 to 1000? I have tried to isolate
groups of tasks in 550/530/520 bands and this performs the
resource levelling (set to Priority, Standard) correctly.
When I close the project however, these values are lost
and all default to 600.
Yours confused, Alan Barrington-Hughes