A
Amit
Hi All,
I am facing a weird problem in Project 2000.
Following is the scenario...
I make a new task 'Task' with duration 10 days and work effort as 55
hours. Now, i assign two resources with units 105% and 95% respectively
and then press ok. To my surprise, the duration changes to 5.26 days
and assignment units change to 72% and 65% respectively.
Now, again , if i manually change the units back to 105% and 95%
respectively, the duration changes to 3.62 days.
Why didn't Project show the duration as 3.62 days at the first
instance?
Any help would be appreciated.
Regards,
Amit
I am facing a weird problem in Project 2000.
Following is the scenario...
I make a new task 'Task' with duration 10 days and work effort as 55
hours. Now, i assign two resources with units 105% and 95% respectively
and then press ok. To my surprise, the duration changes to 5.26 days
and assignment units change to 72% and 65% respectively.
Now, again , if i manually change the units back to 105% and 95%
respectively, the duration changes to 3.62 days.
Why didn't Project show the duration as 3.62 days at the first
instance?
Any help would be appreciated.
Regards,
Amit