M
melissa.pershing
My group has struggled with re-baselining a project (tasks) ever since
I've been here. We're moving to 2003 soon which should help alleviate
some of our problems. Here's a quick scenario.
IT Software Development Project
During Development we had an approved change and the simplified
summary task structure is as such
Initation (complete)
Planning (complete)
Execution
-Development (in progress) BLWrk (858) Wrk (799)
---Task 1 BLWrk (355) Wrk (342)
---Task 2 BLWrk (143) Wrk (181)
---Task 3 BLWrk (360) Wrk (225)
---Task 4 *new task* BLWrk (52) Wrk (52)
Closing
So I baselined Task 4 and all sub-sequent tasks. Then I need to
rebaseline Dev, Execution, and Task 0, correct? However, I would
expect BL Work on Development should just add in the addt'l 52 hours -
making it (910), but it doesn't, instead it copies Wrk (799) into
BLWrk. I've read on why this happens, but I'm not sure it produces
the right reporting results.
I'm more concerned with getting the proper EV information out of the
project after making this approved change. I have been talking myself
into a circle for about 2 hours on this now, but I'm admittedly weak
in the EV arena.
My entire PMO team would appreciate any insight into this frustrating
problem!
Melissa Pershing, PMP
I've been here. We're moving to 2003 soon which should help alleviate
some of our problems. Here's a quick scenario.
IT Software Development Project
During Development we had an approved change and the simplified
summary task structure is as such
Initation (complete)
Planning (complete)
Execution
-Development (in progress) BLWrk (858) Wrk (799)
---Task 1 BLWrk (355) Wrk (342)
---Task 2 BLWrk (143) Wrk (181)
---Task 3 BLWrk (360) Wrk (225)
---Task 4 *new task* BLWrk (52) Wrk (52)
Closing
So I baselined Task 4 and all sub-sequent tasks. Then I need to
rebaseline Dev, Execution, and Task 0, correct? However, I would
expect BL Work on Development should just add in the addt'l 52 hours -
making it (910), but it doesn't, instead it copies Wrk (799) into
BLWrk. I've read on why this happens, but I'm not sure it produces
the right reporting results.
I'm more concerned with getting the proper EV information out of the
project after making this approved change. I have been talking myself
into a circle for about 2 hours on this now, but I'm admittedly weak
in the EV arena.
My entire PMO team would appreciate any insight into this frustrating
problem!
Melissa Pershing, PMP