M
Michael
Hi,
I would like to do the following:
Have a column where I enter in a beginning set of hours, then have a second
column where I record the actual work and then have a third column that shows
the differential between the baseline hours and the actual hours.
I was using Baseline Work 1 and Baseline Work 2 to record the hours, but I
can't figure out how to get the third column to calculate based on those two
columns even though I've added a formula. Is there a better way to do this?
Thank you!
Michael
I would like to do the following:
Have a column where I enter in a beginning set of hours, then have a second
column where I record the actual work and then have a third column that shows
the differential between the baseline hours and the actual hours.
I was using Baseline Work 1 and Baseline Work 2 to record the hours, but I
can't figure out how to get the third column to calculate based on those two
columns even though I've added a formula. Is there a better way to do this?
Thank you!
Michael