Calculate Hours

M

Michael

Hi,
I would like to do the following:
Have a column where I enter in a beginning set of hours, then have a second
column where I record the actual work and then have a third column that shows
the differential between the baseline hours and the actual hours.

I was using Baseline Work 1 and Baseline Work 2 to record the hours, but I
can't figure out how to get the third column to calculate based on those two
columns even though I've added a formula. Is there a better way to do this?
Thank you!

Michael
 
J

JulieS

Hello Michael,

If you used Baseline Work to capture the "beginning set of hours" and
Actual Work to capture actual work, Project will calculate Work
Variance for you.

Take a look at the Work table -- it already has all three fields.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top