Can I run a report in Projects to find a circular relationship?

C

Catfish Hunter

When I open my project it gives an error message that task 1002 has a
successor causing a circular relationship. I took off all the successors and
still get the same error message. In Primavera I can run a report that shows
me the problem. How do I accomplish this in MS Projects?
 
J

Jan De Messemaeker

Hi,

In Project this only happens through links to or from summary tasks.
Eliminate all these and the trouble will disappear.
HTH
 
C

Catfish Hunter

I found one summary task with a successor. Removed the the link and the
project began to calculate one again.
Catfish Thanks JDM
 