Can you rebaseline Cost but not dates?

G

Goobie

The project has been progressing for 5 months but now they have
changed the resource cost & are going backwards to rebill. Is there
anyway to just rebaseline the cost but not the dates?
 
J

JulieS

Hello Goobie,

No, not directly. But you could save a new baseline using one of the
spare BaselineN options and then copy the baseline costs back to the
Baseline field.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top