Hi TJ,
John suggested that you check the setup of your schedule by following
FAQ #5 and you note that you had "complied" -- but your comment below
doesn't seem to indicate that you followed both parts.
I assume from your post below that you have set your settings in the
Tools > Options, Calendar tab to:
Hours per day = 24 hours
Hours per week = 168 hours *not* 7 as you note
Days per month = 31
What is the setting in your calendar under Tools > Change working time?
Are you using the 24 hours calendar as the Calendar tab would seem to
indicate you are?
If you have set the definition of the number of hours per day to 24
hours but your Project calendar only allows 8 working hours per day, it
is natural that the dates do not match as you wish.
Please review FAQ #5 again and again, please let us know:
1) What calendar you are using as the Project calendar? (Check Project >
Project Information)
2) What is the working time definition (Start, End) in the project
calendar under Tools > Change Working Time?
3) What are the working days (Monday through Friday? Sunday to
Saturday?) in the Project calendar?
4) What task type are you using?
5) What version of MS Project are you using including Service Pack
information?
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project