Capacity in MSP_Portfolio_Analyzer vs. Resource Center

J

John Birnstengel

Hi -

Pertains to Project Server 2007: We're trying to understand which of the
capacity fields in the MSP_Portfolio_Analyzer cube in Data Analysis best
match the capacity shown in the resource center resource availability graphs.
The possible fields include Capacity, Base Capacity, and Temporary
Capacity. None of these seem to have numbers anywhere near what we see in
the resource center. Definitions of these fields would be a very helpful
starting point.

Thanks Much, John
 
M

Marc Soester [MVP]

John, it should be the capacity.
When you say that the numbers are wrong, do you also filter the dates in the
data anayser view?
Hope this helps
 
J

John Birnstengel

Thanks for Your Response Mark,

It looks like our capacity range sync job has never run thus we're not
getting the right capacity numbers in the reporting database. We scheduled
it to run in Server Settings > Additional Server Settings.... We're at SP2
plus Aug09 CU. We are not filitering anything. Do you know of a way to
kick-start this?

Best Regards, John
 