Change Event

A

A Burns

In reference to Project 98's Project Change Event, I would
like to use this event to update customized columns that I
have put in place base upon values entered into a
customized column.

I have noticed the Calculate event does not fire when an
update is made to a custom column. However, when using
the Change event I usually get thrown into a infinite
loop. Any suggestions for an alternative plan?

I have a column called Estimated Duration(Duration2). By
default Estimated Duration = Duration. However, if the
Estimated Duration increases, then my custom column Actual
Finish increases by the DateAdd(Finish Date,difference of
Duration - Duration2)

Thanks
A
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top