Hi,
I made a duration custom field and the result is in days, i´m new with
formulas and i don´t know how to display it in hours insteado of days.
I`d apreciate any help

Nacio.
 
J

Jan De Messemaeker

Hi,

Tools, Options, Schedule, Duration is entered in... will reste it for all
custome duration fields (and for summary tasks duration fields)
If you want to customize it for one field only you cannot use duration
fields.
You have to use a number field (in which case it will show without any
mention of the unit) or a text field (where you have to concatenate the unit
to the value calculated).
In both these cases remember duration is calculated in minutes and you may
have to /60
Greetings,
 
I

Ignbell

Thanks a lot Jan! really helped me.
Nacio

Jan De Messemaeker said:
Hi,

Tools, Options, Schedule, Duration is entered in... will reste it for all
custome duration fields (and for summary tasks duration fields)
If you want to customize it for one field only you cannot use duration
fields.
You have to use a number field (in which case it will show without any
mention of the unit) or a text field (where you have to concatenate the unit
to the value calculated).
In both these cases remember duration is calculated in minutes and you may
have to /60
Greetings,
 