How do I adjust a start variance without changing the remaining duration of
another task?
 
D

davegb

Philippa said:
How do I adjust a start variance without changing the remaining duration of
another task?

After you've baselined the project, enter the actual start of the task.
The start variance is the difference between Baseline Start and Actual
Start.
 