Changing timescale in Network diagram

A

Alireza

How do I change timescale to "day of year" in network diagram for start day ,
early start and etc. ?
 
M

Mike Glen

Hi Alireza ,

Welcome to this Microsoft Project newsgroup :)

The only way I can find is to create a new template. Try Format/Box
Styles.../More Templates.../Copy.../give it a name. If you click on the
cell Start, you can now choose the Date Format which has week/day numbers at
the end of the pick list. Repeat for Finish and close down. Now select all
the boxes, Format/Box/and from the Data templates pick list, select your
template/OK.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
A

Alireza

Hi Mike ,
Thank you very much for reply!
I think my quastion was in bad sentence.
I want to change my "Date format" to day of year. But in data template
definition we haven't this option in "date format". Anyway I can see this
option in Format.../ Time scale.../ Label ---> (day of week) in gantt chat
view. And now I want this in network view! I want to show what day of year is
my task start date in network diagram.
please help me if there is any answer.
Best regards.
 
M

Mike Glen

My response gives you all that is available in the Network view. As what
you want isn't there, you're out of luck :(

Mike Glen
Project MVP
 