Steve said:
I have a master project linking to a number of sub projects, if one of the
underlying plans has a circular ref in it, does that disable calculation in
the master project and therefore the other project plans are not being
calculated?
Steve,
I guess it depends on the extent of the circular relationship. Given a
circular relationship you are lucky that the master will open at all. I
suggest you address the cause of the circular relationship and then your
question will go away.
First turn off automatic calculation and open the master. Then check
that there are no links on any summary lines in any project. If that's
clear, you can either manually trace the link path of the circular
relationship and eliminate it or you might try using fellow MVP, Jack
Dahlgren's Trace macro. You can find that macro on Jack's website at:
http://masamiki.com/project/macros.htm
Hope this helps.
John
Project MVP