Circular Reference

B

Bob Vardell

I keep getting an error when I open my project that task 9108 120 has links
that creat a circular reference. I delete the links to this task and then
the one above it has that error. When I delete that link, the one above IT
gets the error....See the Pattern?

How do I fix this problem without deleting all the links in the 10000 line
schedule?

Thanks,
Bob
 
M

Mike Glen

Hi Bob,

Welcome to this Microsoft Project newsgroup :)

The most common reason for circular references is when Summary tasks are
linked. Filter for summary tasks and remove all the links.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 